Challenge

When the Ministère des Transports Québec embarked on a project to reconstruct a steel and concrete decked bridge on L’Autoroute 40, Félix-Leclerc in Berthierville, just outside Montreal, there was a requirement to install a temporary detour solution to ensure traffic was not impacted.

The original bridge was approaching end-of-life and had required additional bracing in recent years. The project to replace the bridge was a major one scheduled to last two years. L’Autoroute 40 runs along the north shore of the St. Lawrence River and is one of two major connections between Montreal and Quebec City. The site of the bridge is on a major interstate serving the second largest city in Canada, so it was imperative to install a detour bridge in a timely and efficient manner.

Solution

The bridge solution used for the detour was a 67.5 metre span Mabey Delta™ with an 8 metre road width, parapet system and 70mm asphalt decking. This was the first Mabey Delta™ bridge system installed in the province of Quebec, and was supplied by Algonquin Bridge, Mabey’s distributor in the territory.

Installation of the bridge was by a cantilevered launch from one side without lifting equipment. Roxboro Excavation Inc, the contractor for the installation, erected and launched the bridge with guidance from Algonquin’s on-site advisors. The steel decking and parapet systems were installed prior to launch in order to reduce the amount of work done over the river after installation.

The launch of the bridge was executed from one side using a fully-cantilevered sequence with a 10-bay launch nose. When the bridge and team were ready, on-site equipment nudged the structure across the river to the opposite side.

The Mabey Delta™ bridge system uses innovative 4.5 metre long ‘Delta’ panels and is able to achieve clear spans of up to 90 metres. The panels are bolted to top and bottom chord members to form the side trusses, carrying the applied loads between abutments or intermediate piers. The Mabey Delta™ combines the best in off-site fabrication with high-speed construction and rapid installation. With specially designed Mabey Delta™ deck and pre-camber system, the system can be configured for single or multiple span bridging in road widths up to 10.5 metres (three lanes) and provides superior permanent or long-term temporary long-span bridging for major highway applications.

Result

The detour bridge at Berthierville was installed with ease and is providing a robust detour solution for the two years it will take to install a permanent bridge. The Ministère des Transports Québec will own the system once this deployment is complete and has already expressed an intention to reconfigure and redeploy it for future projects. With a minimum life of 25 years and a capacity to accommodate average traffic levels of 13,000 vehicles per day at a speed of 70 km/h, the Ministère des Transports Québec now has a reusable bridge solution that will undoubtedly be employed in subsequent major infrastructure work across the territory.

Products

Mabey Atlas Bridge

Ideal for permanent highway bridges and inner city flyovers, our Atlas bridges provide a lightweight super-structure which is pre-fabricated for rapid installation.

view product

Mabey Atlas Light Bridge

A lightweight steel bridge which is fully pre-fabricated, galvanised and quick to install in permanent and temporary applications.

view product

Mabey Compact 200

Mabey’s most popular modular bridging system. Supplied in a variety of spans and widths, and configured from pre-engineered components for ease of installation

view product

Mabey Composite Bridge

Our composite bridges are rapid-build steel solutions combined with concrete decks, and supplied with a comprehensive Design and Fabricate service to support permanent bridging applications

view product

Mabey Delta Bridge

Our Delta Bridges provide a proprietary, permanent modular bridging solution well-suited to long span bridging requirements in both main highway and rural applications

view product

Mabey Pedestrian Bridge

Pedestrian bridges are quick and easy to erect, the Mabey solution is designed for both permanent and temporary pedestrian applications

view product

browse more products

Related Projects

Enabling quick, safe and efficient construction site access in Australia

SectorsConstruction, Infrastructure, Transport

CategoriesBridging, Engineering and Project Services

LocationCapalaba, South East Queensland, Australia

view project

Heatherton, Canada

SectorsGovernment, Infrastructure, Transport

CategoriesBridging, Engineering and Project Services, Major Projects

LocationCanada

view project

McCutcheon Bridge, Canada

SectorsConstruction, Humanitarian Aid and Disaster Relief, Infrastructure

CategoriesBridging

LocationBracebridge, Ontario, Canada

view project

view all projects